outline of the construction
Source: Shizuoka Geographic Information System
The target schedule of、Building No.1~Building No.12 and Building No.14 a total of 13 building Units for construction is from year 2021 to year 2029.
The rebuilding work is roughly divided into four sections, and the existing building is demolished and the new building is repeatedly built on the site.
In addition, in the surplus land in the southeast (near Building No.5 to Building No.7) created by the rebuilding, commercial facilities and facilities for the elderly will be constructed after the completion of No.4 construction Area.
Sanaruko Prefecture Housing Unit before maintenance
Before

No.1construction Area
Moving Period Month of April~May of year 2022
No.2construction Area
Moving Period Approximately Month Of December of Year 2023
No.3construction Area
Moving Period Approximately Month Of November of Year 2025
No.4construction Area
Moving Period Approximately Month Of December of Year 2027
No.2 construction Area~No.4 construction Area Moving Period is assumed
Sanaruko Prefecture Housing Unit after maintenance
After

Construction Schedule
The buiduing Number is subject to change
No.1construction Area
- 2021-2023
- Building No.12 disassembly(2022)
- 2022-2023
- A-1、A-2、B-3 New Building
No.2construction Area
- 2023-2025
- Building No.1、Building No.8〜11 disassembly
- 2024-2025
- B-1、B-3、C-2 New Building
No.3construction Area
- 2025-2027
- Building No.2〜4 disassembly
- 2026-2027
- C-1、D、E New Building
No.4construction Area
- 2027-2028
- Building No.5〜7
- ※Surplus Land Maintenance、Building No.14 disassembly、No 4 construction AreaAfter Completion