Rebuilding construction

HOME > Rebuilding construction

outline of the construction

Source: Shizuoka Geographic Information System

The target schedule of、Building No.1~Building No.12 and Building No.14 a total of 13 building Units for construction is from year 2021 to year 2029.
The rebuilding work is roughly divided into four sections, and the existing building is demolished and the new building is repeatedly built on the site.
In addition, in the surplus land in the southeast (near Building No.5 to Building No.7) created by the rebuilding, commercial facilities and facilities for the elderly will be constructed after the completion of No.4 construction Area.

Sanaruko Prefecture Housing Unit before maintenance

Before

Sanaruko Prefecture Housing Unit before maintenance

No.1construction Area

Moving Period Month of April~May of year 2022

No.2construction Area

Moving Period Approximately Month Of December of Year 2023

No.3construction Area

Moving Period Approximately Month Of November of Year 2025

No.4construction Area

Moving Period Approximately Month Of December of Year 2027

No.2 construction Area~No.4 construction Area Moving Period is assumed

Sanaruko Prefecture Housing Unit after maintenance

After

Sanaruko Prefecture Housing Unit after maintenance

Construction Schedule

The buiduing Number is subject to change

No.1construction Area

2021-2023
Building No.12 disassembly(2022)
2022-2023
A-1、A-2、B-3 New Building

No.2construction Area

2023-2025
Building No.1、Building No.8〜11 disassembly
2024-2025
B-1、B-3、C-2 New Building

No.3construction Area

2025-2027
Building No.2〜4 disassembly
2026-2027
C-1、D、E New Building

No.4construction Area

2027-2028
Building No.5〜7
※Surplus Land Maintenance、Building No.14 disassembly、No 4 construction AreaAfter Completion